Menu
Engineering: Roadway Projects
Below are compilations of transportation and building projects in which Collin County departments play a role. We've sorted these out in an effort to show residents what is currently happening with roadways throughout the county.
Construction start: 26.8% Complete; End: September 2026
Construction: 100% Complete; Ended: March 2026
Construction: 99% Complete; Tentative End of Construction: April 2026
Construction: 55% Complete; Tentative End of Construction: Spring 2027
Construction: 40% Complete; Tentative End of Construction: September 2026
- Project
- Coit Rd.
- Limits
- Vest Ln to Choate Pkwy
- Status
- Construction: 0% Complete, Tentative Start of Construction: End January 2027
- Project
- Coit Rd. Intersection Improvements
- Limits
- Coit Rd. at First Street, Prosper Trail and Frontier Parkway
- Status
Construction start: 26.8% Complete; End: September 2026
- Project
- Dallas Pkwy
- Limits
- Lebanon Rd. to Panther Crk Pkwy.
- Status
- Completed Feb 2026
- Project
- Fairview Pkwy
- Limits
- Medical Dr. to Ridgeview Dr.
- Status
- Completed Feb 2026
- Project
- Frankford Rd.
- Limits
- SH289 (Preston Rd) to Coit Rd
- Status
Construction: 100% Complete; Ended: March 2026
- Project
- Leonard Rd.
- Limits
- Foster Crossing to Collin County Outer Loop
- Status
Construction: 99% Complete; Tentative End of Construction: April 2026
- Project
- Lucas Rd.
- Limits
- FM 2551 to Country Club Rd.
- Status
- ROW/90% Design; Tentative Start of Construction: June 2026
- Project
- McMillen Dr.
- Limits
- McCreary Rd. to Country Club Rd.
- Status
Construction: 55% Complete; Tentative End of Construction: Spring 2027
- Project
- N. Greenville Ave
- Limits
- CR 850 to ISD Property Line
- Status
Construction: 40% Complete; Tentative End of Construction: September 2026
- Project
- Wilmeth Rd.
- Limits
- Lake Forest Dr. to Hardin Blvd.
- Status
- Substantially Complete March 2026
60% Design and ROW acquisition underway
Design in Progress
90% Design; Tentative Start: Summer 2026
Construction: 38.6% Complete, Tentative End of Construction: Late 2027
- Project
- CR 398
- Limits
- Status
60% Design and ROW acquisition underway
- Project
- CR 557
- Limits
- US 380 to SH 78
- Status
Design in Progress
- Project
- FM 546 Phase I
- Limits
- CR 393 to US 380
- Status
90% Design; Tentative Start: Summer 2026
- Project
- FM 546 Phase II
- Limits
- Airport Dr. to CR 393
- Status
- County is managing the schematic for TxDOT. Schematic is 95% complete.
- Project
- Outer Loop - Second Service Roads
- Limits
- Collin County Line to Choate Pkwy
- Status
- 60% Design; Tentative Start of Construction: Mid 2026
- Project
- Outer Loop Segment 1
- Limits
- US 75 to TX 121
- Status
- Schematic Design 30% Complete
- Project
- Outer Loop Segment 3
- Limits
- FM 2478 to US 75
- Status
- Construction: Substantially Complete; Tentative End of Construction: April 2026
- Project
- Outer Loop Segment 5
- Limits
- TX 121 to CR 655
- Status
- Alignment Study Underway. 2nd Public Meeting to be held Q2 2026
- Project
- Outer Loop Segments 2 &4
- Limits
- US 380 to Rockwall County Line
- Status
- Schematic Design is in Progress
- Project
- Outer Loop/US 75 Intersection
- Limits
- Status
- Intersection Study in Progress
- Project
- Park Blvd
- Limits
- Parker Rd to Spring Creek Pkwy
- Status
Construction: 38.6% Complete, Tentative End of Construction: Late 2027
- Project
- SE Mobility Study
- Limits
- Status
- Report Completed December 2024
For a comprehensive list of TxDOT projects and information, please click on links below: